SY/T 0033-2020 in English
VALIDSpecification for design of oil-gas field electrical power substation and distribution
- Issued on:2020-10-23
- Implemented on:2021-02-01
- File Format:PDF
- Delivery:Via email within 10 business days
$941.00
Introduction
Interpretation of the core content of the standard
| Technical module | 2009 version | Main revision points of the 2020 version |
|---|---|---|
| Load classification | Three-level classification system | Added the definition of particularly important loads, and refined the classification of natural gas liquefaction plants |
| Power supply system | Basic requirements for dual circuits | Clearly define the dual power supply configuration plan (Appendix A) and T-connection conditions for the public grid |
| Substation design | Conventional substation | New technical requirements for prefabricated substations (Article 6.1.3) |
Key technical requirements
1. Load classification management
The standard divides oil and gas field loads into three levels, among which emergency shut-off valves and automatic control systems are listed as particularly important loads, with the following requirements:
- Level 1 load: Dual power supply + emergency power supply must be used (Article 3.2.1)
- Level 2 load: T-connection to the public grid is allowed (Article 3.2.2)
- Natural gas liquefaction plant: Classification according to processing volume (Article 3.1.10)
2. Power supply and distribution system design
Typical case: A 500×10⁴m³/d natural gas purification plant uses a 35kV dual power supply line and is equipped with two on-load tap-changing transformers (Article 5.2.9). After reactive power compensation, the power factor reaches 0.95 (Article 5.4.2).
Allowable voltage deviation:
- Electric motor: ±5% (+5%~-10% in special cases)
- Lighting: ±5% in general places, +5%~-10% in remote areas
3. Substation configuration
It is recommended to use prefabricated substation (Article 6.1.3), requirements:
- The comprehensive automation rate of stations of 35kV and above is 100%
- Transformer load rate is 60%-85% (oil pump transformer ≥30%)
- Oil-free circuit breakers are used for high-voltage equipment (Article 6.5.3)
Implementation suggestions
Precautions in the design stage
| Phase | Work focus |
|---|---|
| Feasibility study | Load classification confirmation, power supply scheme comparison |
| Construction drawing design | Single-phase load conversion (Article 4.2.3), harmonic control |
New energy application
Solar power generation can be used in remote well sites (Article 3.2.2), and the supporting battery capacity is calculated based on 4h accident discharge (Article 6.6.1).

Loading PDF document...
Error loading PDF. Please make sure the file is valid and try again.
We also recommend
-

SY/T 5717-1995 in English
Single well clastic reservoir evaluation
1995-07-13 -

SY/T 5429-1991 in English
Small diameter flow moisture tester
1992-01-15 -

SY/T 6280-1997 in English
Health safety and environmental management specification for seismic crew
1997-07-17 -

SY/T 5758-2018 in English
Lubricants used in drilling fluid. Lubricating beads
2018-10-29 -

SY/T 10023.1-2020 in English
Method of offshore oiVgas field development project economic evaluation-Part 1:Self-financed offshore oil/gas field
2020-10-23 -

SY/T 6243-2009 in English
Specifications for wellsite drilling monitoring of oil and gas exploration well
2009-12-31 -

SY/T 5164-2016 in English
Roller cone drill bits
2016-12-05 -

SY/T 7397-2017 in English
Recommended practice for flowline connectors and jumpers
2017-11-15 -

SY 5049-1991 in English
Drilling slips
1991-11-20