Introduction
Analysis of the core content of the standard
Major technical changes
| Revision items | Requirements of the 2007 version | Requirements of the 2020 version | Technical impact |
|---|---|---|---|
| Basic error | ≤0.2% FS | ≤0.5% FS (≤0.3% for >50mm) | Relax the accuracy requirements but distinguish the measuring range |
| Anti-electromagnetic interference | SL 268-2001 | GB/T 17626.3 | Adopting international general standards |
| New tests | None | Surge immunity/environmental adaptability | Enhanced equipment reliability |
Detailed explanation of key technical indicators
Core performance parameters
- Resolution: ≤0.02mm (verified by grating ruler)
- Operating temperature: -20℃~+60℃ (extended original -10℃~+50℃ range)
- Insulation resistance: ≥50MΩ (100V test voltage)
Implementation and application suggestions
Key points for project selection
- Give priority to equipment with a range of >50mm (with stricter error requirements)
- A surge immunity test report must be included during acceptance
- Perform stability verification regularly (30 days of continuous monitoring)
Maintenance precautions
- Storage environment humidity ≤85%
- Recalibration is required after transportation
- Mandatory type test every 5 years
Standard Evolution Analysis
This standard reflects the mature application of CCD sensor technology in the field of dam monitoring. The main revisions are:
- Electromagnetic compatibility requirements are in line with international standards
- New environmental adaptability indicators
- Improve product life cycle management requirements
Sample only — not a preview of DL/T 1061-2020

Loading PDF document...
Error loading PDF. Please make sure the file is valid and try again.
We also recommend
-

DL/T 790.12-2001 in English
Distribution Automation Using Distribution Line Carrier Part 1: General Provisions Part 2: Guidelines for Formulation of Specifications
2001-12-26 -

DL 5073-1997 in English
Code for seismic design of hydraulic structures
1997-08-04 -

DL/T 5240-2010 in English
Technical code for design and calculation of combustion system of fossil-flred power plant
2010-05-01