GB/T 44273-2024 in English
VALIDSpecification for operation and management of hydropower projects
- Issued on:2024-08-23
- Implemented on:2025-03-01
- File Format:PDF
- Delivery:Via email within 5 business days
$359.00
《GB/T 44273-2024水力发电工程运行管理规范》由624(国家能源局)归口,主管部门为国家能源局。
Introduction
1. General requirements
The core goal of the hydropower project operation management specification is to ensure the safe, efficient and sustainable operation of the project. According to GB/T 44273-2024, the operation management unit needs to formulate corresponding management systems and technical regulations based on the characteristics of the project and the actual operation situation. These systems should include:
- Operation management system
- Operation procedures
- Emergency plan
- Annual safety production plan
2. Operation management of hydraulic structures
Hydraulic structures are the core facilities of hydropower stations, and their safety is directly related to the stability and safety of the entire project. The following are the specific requirements for hydraulic structures in the specification:
2.1 Safety monitoring
The operation management unit must establish a complete safety monitoring system, including the following:
- Monitoring items: displacement, tilt, cracks, etc.
- Monitoring frequency: Determined according to the project stage and risk level.
- Data processing: Regularly analyze monitoring data and evaluate the safety status of the building.
Case study
A large hydropower station successfully discovered and promptly repaired tiny cracks in the dam body by establishing an automated safety monitoring system, avoiding potential safety accidents.
3. Equipment and facility operation management
3.1 Monitoring and inspection
Monitoring and inspection of equipment and facilities are key links to ensure their normal operation. Specification requirements:
- Real-time monitoring using a computer monitoring system.
- Periodic inspections are carried out, and abnormalities are handled promptly.
3.2 Operation and control
The start-up, shutdown and operation of the equipment must strictly comply with relevant regulations. For example:
- The start and stop procedures of the turbine must comply with the DL/T 710 standard.
- The operation of the gates and flood discharge facilities must be carried out according to the dispatching instructions.
4. Management of the Reservoir and Project Areas
4.1 Management of the Reservoir Area
The focus of reservoir area management is:
- Monitor the stability of the reservoir bank slope.
- Regularly clean up floating objects and garbage.
- Carry out ecological monitoring and protection work.
4.2 Management of the Project Area
Activities within the project protection area must be strictly controlled to avoid harm to the hub buildings. For example:
- Dangerous activities such as sand mining and blasting are prohibited within the protection area.
- Regularly inspect the boundaries and facilities of the project area.
5. Dispatching Management
5.1 Hydrological and Meteorological Observation
Hydrological and meteorological data are the basis for dispatching decisions. Specification requirements:
- Establish a sound automatic water situation observation and reporting system.
- Develop a flood forecasting plan based on the characteristics of the river basin.
5.2 Flood Control Dispatching
Flood control dispatching is an important part of ensuring downstream safety. Specific requirements include:
- Prepare an annual flood season dispatching and operation plan.
- Obey the unified command of the flood control department.
6. Safety, Health and Environmental Management
6.1 Safety and Emergency Management
Operating units need to establish and improve safety management systems, including:
- Carry out safety inspections regularly.
- Develop emergency response plans and organize drills.
6.2 Occupational health management
Occupational health is an important part of protecting the rights and interests of employees. Regulatory requirements:
- Regularly test occupational disease hazards in the workplace.
- Provide employees with protective equipment that meets standards.

Loading PDF document...
Error loading PDF. Please make sure the file is valid and try again.
We also recommend
-

GB/T 44634-2024 in English
Basic terminology of hydropower engineering
2024-09-29 -

GB/T 50927-2013 in English
Code for Risk Management of Large and Medium-sized Hydropower Project Construction
2013-11-01 -

GB/T 40222-2021 in English
Guide for smart hydropower plant
2021-05-21 -

GB/T 18110-2016 in English
Electromechanical equipment guide for small hydroelectric installations
2016-06-14 -

GB/T 32506-2016 in English
Gode of operation and maintenance for excitation system of pumped storage unit
2016-02-24