SY/T 5980-2020 in English
VALIDWell test design specifications for exploration well
- Issued on:2020-10-23
- Implemented on:2021-02-01
- File Format:PDF
- Delivery:Via email within 5 business days
$582.00
| Standard No: | SY/T 5980-2020 |
| Document status: | VALID |
| Title in English: | Well test design specifications for exploration well |
| Title in Chinese: | 探井试油设计规范 |
| Language: | English |
| File Format: | Electronic (PDF) |
| Delivery: | Via email within 5 business days |
| Issued on: | 2020-10-23 |
| Implemented on: | 2021-02-01 |
| Superseding: |
SY/T 5980-2009 Specification for design of Well test of exploration well
|
| Professional Classification: | SY-Oil & Gas |
| Related Keywords: | geological design
design specifications design parameters collaborative design design specify |
| Related Topics: | Oil Trim Design
Explore LNA probe design Test oil Agricultural Well Design Oil well design industry Test board design specifications Flow meter well design sy/t 7494-2020 sy/t 7466-2020 sy/t 7468-2020 |
Introduction
Standard Revision Background and Technology Evolution
SY/T 5980-2020, as the core standard of the oil and gas industry, replaces the 2009 version and achieves three major technological breakthroughs: 1) Adding well control and HSE risk identification system; 2) Improving high temperature and high pressure well design parameters; 3) Introducing digital design templates. This standard responds to the technical needs of my country's shale gas, tight oil and other unconventional resource development.
Comparison of core changes
| Technical dimensions | 2009 version | 2020 version | Upgrade points |
|---|---|---|---|
| Risk control | Basic well control requirements | Full process risk identification (4.6/5.14 clauses) | New geological factors risk matrix analysis |
| Design structure | Three-stage discrete design | Integrated collaborative design (Chapter 7) | Establish a change linkage mechanism |
| Special working conditions | Mainly conventional well design | Specify the design of four types of special wells (Clause 1.3) | Sulfur-containing wells require separate material selection |
Guidelines for the implementation of key design elements
Core requirements for geological design
According to Clause 4.4, the production capacity forecast must include:
- Three-phase analysis of fluid properties (oil, gas, water)
- Calculation of formation pressure gradient (need to reference adjacent well data)
- The perforation plan needs to be marked with the negative pressure difference range
Wellbore integrity management for engineering design
Clause 5.3 requires the establishment of a double barrier system:
- Primary barrier: tubing + packer combination
- Secondary barrier: casing + wellhead equipment
- Triaxial stress verification is required (safety factor of ultra-deep wells ≥1.25)
Key points for special working conditions
For hydrogen sulfide wells (H2S ≥50ppm):
- The pipe material must meet the ISO 15156 standard
- The ground process is equipped with a two-stage desulfurization device
- The emergency response time is controlled within 15 minutes
Implementation suggestions and common problems
Design change management (Chapter 7): The three versions of the geological, engineering and construction design documents need to be updated simultaneously, and the change order must include:
- Technical justification for the reason for the change
- Parameter comparison table before and after the modification
- New risk assessment report

Loading PDF document...
Error loading PDF. Please make sure the file is valid and try again.
We also recommend
-

SY/T 4069-1993 in English
Petroleum Construction Quality Inspection and Evaluation Standards oilfield steel container production (with the provisions stated)
1993-09-09 -

SY/T 5429-1991 in English
Small diameter flow moisture tester
1992-01-15 -

SY/T 5117-1996 in English
Rock pyrolysis analysis method
1996-12-31 -

SY/T 313-1996 in English
Technical specifications for the design and construction of Tanhai Petroleum Engineering Terminal
1996-12-03 -

SY 5400-1991 in English
Casing power tongs for oil drilling
1991-11-20 -

SY/T 6268-1996 in English
Recommended Practices for Selection of Tubing and Casing
1996-12-31 -

SY/T 5586-1993 in English
Contract specifications for the introduction of complete sets of equipment for the petroleum industry
1993-03-27 -

SY/T 5368.5-1995 in English
Rock thin section identification method carbonate rock
1995-12-25 -

SY/T 5899-1993 in English
Technical conditions of hydraulic power instrument
1994-01-06 -

SY/T 5850-1993 in English
Sulfonated asphalt for drilling fluid (paste)
1993-11-16