Scope
主要内容包括以下部分:
一、工厂建设管理模式
A、工厂建设模式
The construction mode of the factory can be categorized into self-built and delegated modes based on different construction subjects.
Self-built mode refers to a joint venture between the government and enterprises for factory projects, where the project company organizes and completes the entire engineering construction process.
Delegated construction mode involves a joint venture between the government's platform company and enterprises. During the construction period, it is handled by a delegated company from the platform company, which constructs the factory according to the design drawings provided by the project company; after the engineering passes inspection and meets national and industry standards (90 days), it will be handed over for use once its functions are confirmed.
B、工厂工程承包模式
It is recommended that the construction of the factory adopt an integrated engineering contracting model. Under this mode, the owner entrusts the entire project to a contractor who is responsible for designing, purchasing materials, and constructing the building. The contractor will ensure the progress, quality, safety, schedule, and cost of the construction. Ultimately, they will deliver a completed and inspected project that meets contract requirements and usage standards.
Project consultancy services should also be engaged during the construction process due to the specialized nature of large-scale cleanrooms in factory projects.
二、工厂选址要求
The selection of a factory site includes both site environmental requirements and basic infrastructure requirements (7 utilities and leveling).
Site environmental requirements include:
a) Site leveling;
b) Area requirements;
c) Water supply and drainage requirements;
d) Natural gas requirements;
e) Electrical requirements;
f) Water environment requirements;
g) Requirements for the recycling of hazardous materials;
h) Noise environment requirements;
i) Other.
Basic infrastructure requirements (7 utilities and leveling) refer to specific construction planning requirements, including:
a) Road access
b) Water supply
c) Drainage
d) Electricity
e) Communication
f) Gas supply
g) Hot water supply
h) Site leveling
(4) 工厂报批报建流程
The approval and registration process for the factory can follow the following sequence:
a) Project initiation procedures;
b) Procedures for obtaining a state-owned land use certificate;
c) Procedures for obtaining a construction land planning permit;
d) Procedures for obtaining a construction engineering planning permit;
e) Drawing review procedures;
f) Tendering and bidding procedures;
g) Construction project commencement procedures;
h) Environmental impact assessment procedures;
i) Energy consumption evaluation procedures;
j) Safety/occupational health evaluation procedures;
k) Fire safety approval procedures;
l) Other.
(5) 工厂开工条件
The factory can commence construction after the following conditions are met:
a) Feasibility study of the project;
b) Project signing;
c) Site selection;
d) Formation of a project team;
e) Project filing;
f) Obtaining a construction engineering planning permit;
g) Tendering and bidding;
h) Signing contracts for process equipment procurement;
i) Signing financing agreements;
j) Processing land procedures;
k) Design of construction drawings;
l) Environmental impact, safety, energy consumption, occupational health, and fire safety reviews;
m) Obtaining a construction permit.
(6) 施工及变更管理
The management of the construction and change process can include:
a) Quality management;
b) Schedule management;
c) Safety management;
d) Change management procedures.
(7) 工厂验收管理
Management of factory acceptance can include:
a) Structural inspection management;
b) Interior decoration inspection management;
c) Air system inspection management;
d) Gas system inspection management;
e) Water system inspection management;
f) Chemical material supply system inspection management;
g) Electrical distribution system inspection management;
h) Automation control system management;
i) Equipment installation acceptance management;
j) Fire protection system acceptance management;
k) Anti-static facility acceptance management;
l) Engineering inspection management;
m) Clean room acceptance management.