DL/T 782-2001 in English
VALIDCode of start-up & completion acceptance for power transmission & distribution project of 110kV and above
- Issued on:2001-10-08
- Implemented on:2002-02-01
- File Format:PDF
- Delivery:Via email within 5 business days
$321.00
| Standard No: | DL/T 782-2001 |
| Document status: | VALID |
| Title in English: | Code of start-up & completion acceptance for power transmission & distribution project of 110kV and above |
| Title in Chinese: | 110kV及以上送变电工程启动及竣工验收规程 |
| Language: | English |
| File Format: | Electronic (PDF) |
| Delivery: | Via email within 5 business days |
| Issued on: | 2001-10-08 |
| Implemented on: | 2002-02-01 |
| ICS Classification: | 27.100-Power stations in general |
| Chinese Classification: | F22-Electric power system equipment installation testing |
| Professional Classification: | DL-Electricity |
| Related Keywords: | completion acceptance
start-up acceptance power transmission new power transmission distribution project |
| Related Topics: | substation
start up completed Substation project Substation project t project start Initiate acceptance procedures Completion acceptance Quality acceptance and assessment of power substation projects Chromatography acceptance process and dl/t782-2023 t/cec 782 Completion acceptance of electrolytic aluminum project |
本规程适用于110kV及以上的各类新建送变电工程的启动及竣工验收。规模很小的工程和110kV以下送变电工程的启动验收可参照执行。国外成套设备进口的工程还应接合同的规定进行启动及竣工验收。
Scope
This procedure applies to the start-up and completion acceptance of all types of new power transmission and transformation projects of 110kV and above. The start-up acceptance of small-scale projects and power transmission and transformation projects below 110kV can be implemented as a reference. Projects for imported complete sets of equipment from abroad should also be started and completed for acceptance in accordance with the provisions of the contract.

Loading PDF document...
Error loading PDF. Please make sure the file is valid and try again.
We also recommend
-

DL/T 5403-2007 in English
Specification for commissioning and quality acceptance and evaluation of flue gas desulphurization for coal-fired power plant
2007-12-03 -

DL/T 812-2002 in English
Insulators string for overhead lines with a normal voltage above 1000V-AC power arc test method
2002-04-27 -

DL/T 851-2004 in English
Acceptance tests for combined-cycle power plants
2004-03-09