SL 168-2012 in English
VALIDThe acceptance code for construction of small hydropower station
- Issued on:2012-11-23
- Implemented on:2013-02-23
- File Format:PDF
- Delivery:Via email within 1~3 business days
$1,291.00
为加强小型水电站建设工程的建设管理,保证工程验收质量,使小型水电站建设工程的验收制度化、规范化,制定本标准。本标准适用于新建的总装机容量50 MW及以下、1.0MW及以上的小型水电站建设工程的验收。改扩建的小水电工程和新建的总装机容量1.0MW以下的小水电站工程验收可参照执行。
Introduction
Background of Standard Revision and Scope of Application
The 2012 version of the regulations has undergone structural adjustments based on SL 168-96, adding five new chapters such as Sub-project Acceptance and Unit Project Acceptance, and clearly limiting the scope of application to newly built small hydropower projects of 1-50MW. The key points of the revision include:
| Revision dimensions | 1996 version | 2012 version |
|---|---|---|
| Acceptance classification | 3 types of acceptance | 6 types of graded acceptance |
| Mandatory provisions | No clear mark | 1.0.6 bold mandatory |
| Acceptance document requirements | Not systematically specified | 19 normative appendices |
Core acceptance process and technical specifications
1.
Acceptance led by the project legal person includes:
- Acceptance of sub-projects: Start within 5 working days after the completion of all unit projects
- Acceptance of unit projects: Quality supervision agencies must be notified in advance
- Acceptance of contract project completion: Settlement and site cleanup must be completed
Typical case: Unit startup acceptance
A 2×10MW power station adopts a 72-hour load test:
- The trial operation command group prepares the startup test procedure
- After completing the no-load operation inspection, enter the rated load continuous operation
- The 6-12 month trial production period is included in the acceptance cycle
Key control points
1. Mandatory Provisions
Article 1.0.6 clearly stipulates: "Projects that have not been accepted or have failed acceptance should not be put into use", and violators shall bear legal responsibility.
2. Special requirements for stage acceptance
| Acceptance type | Preconditions | Technical documents |
|---|---|---|
| Acceptance of diversion and interception | Relocation completion + flood control plan approval | Appendix F |
| Acceptance of sluice storage | Safety appraisal report + observation data | Appendix G |
Implementation suggestions
- Data preparation: Prepare 27 types of required data and 28 types of reference files according to Appendix A/B
- Time control: The acceptance report should be filed within 20 working days after passing the review
- Dispute resolution: The acceptance conclusion must be agreed by 2/3 of the members, and major disagreements must be reported to the water administration department for a decision

Loading PDF document...
Error loading PDF. Please make sure the file is valid and try again.
We also recommend
-

SL 275-2001 in English
Field test methods for nuclear density-moisture gauges
2002-01-28 -

SL 19-2001 in English
Compilation rules of final account for completion of water capital construction project
2001-02-08