GB/T 39208-2020 in English
VALIDCode of practice for installation and commissioning of retractable azimuth thruster
- Issued on:2020-10-11
- Implemented on:2021-05-01
- File Format:PDF
- Delivery:Via email within 5 business days
$359.00
| Standard No: | GB/T 39208-2020 |
| Document status: | VALID |
| Title in English: | Code of practice for installation and commissioning of retractable azimuth thruster |
| Title in Chinese: | 可伸缩式全回转舵桨装置安装与调试规程 |
| Language: | English |
| File Format: | Electronic (PDF) |
| Delivery: | Via email within 5 business days |
| Issued on: | 2020-10-11 |
| Implemented on: | 2021-05-01 |
| ICS Classification: | 47.020.99-Other standards related to shipbuilding and marine structures |
| Chinese Classification: | U16-Auxiliary vessels and survey vessels |
| Professional Classification: | GB-National Standard |
| Related Keywords: | rod installation
paddle installation base test ≤0.05mpa soap water leak test installation process points flatness base plate installation ≤1mm laser plane meter shaft retractable azimuth thruster introduction interpretation |
| Related Topics: | debugging
telescopic Installation and commissioning process Processing paddle GBT39208 GB/T 39208-2020 gjb6850 rudder device |
《GB/T 39208-2020可伸缩式全回转舵桨装置安装与调试规程》由TC12(全国海洋船标准化技术委员会)归口,主管部门为国家标准化管理委员会。
Introduction
Interpretation of the core content of the standard
GB/T39208-2020 is my country's first special installation and commissioning standard for retractable full-rotation propeller devices, which is applicable to two typical structures of fixed propulsion motors (vertical/horizontal) and follow-up vertical ones. The standard establishes a complete quality indicator system from the dimensions of base processing accuracy (±5mm), seal ring contact surface flatness (≤1mm), shaft alignment (radial/axial deviation), etc.
Comparison of key technical indicators
| Parameters | Installation phase | Allowable deviation | Detection method |
|---|---|---|---|
| Base plane height difference | Base processing | ±5mm | Total station measurement |
| Sealing surface flatness | Base plate installation | ≤1mm | Laser plane meter |
| Shaft radial deviation | Alignment and debugging | Equipment requirements | Dial gauge test |
| Air tightness pressure | Sealing test | ≤0.05MPa | Soap water leak test |
Installation process points
1. Base processing stage
It is necessary to ensure that the center line of the machining equipment is aligned with the center line of the telescopic paddle installation base, and the panel thickness is not less than the theoretical value. The sealing ring area is surface treated according to the requirements of CB/T3802.
2. Guide rod installation and debugging
During the full-stroke telescopic test, the gap around the guide rod and the sleeve must be kept uniform, and the thickness error of the adjustment gasket must be controlled within ±0.1mm. The welding of the underwater support seat must comply with the CB/T3558 secondary weld standard.
3. Shaft alignment control
The axial/radial deviation between the output end of the propulsion motor and the input end of the retractable propeller must be checked using a laser alignment instrument, and a secondary alignment review must be performed after launching.
Key debugging process
Mooring debugging
Includes 12 core tests:
- Auxiliary system pressure test (30min continuous operation)
- Full rotation effectiveness test (0°-360° response time ≤15s)
- 25%-50%-75% load step test
Navigation debugging
Key verification:
- Dynamic stability at 100% rated power
- Controllable pitch propeller pitch calibration (zero calibration error ≤0.5°)
- Response time of full reverse thrust condition
Standard implementation recommendations
1. Welding quality control: 100% UT inspection of base welds is required, and acceptance is in accordance with CB/T3559-2011 Level I
2. Bolt preload management: Hydraulic tensioner is required for bolts above M36, and torque deviation is ≤±5%
3. Debugging data record: It is recommended to use the standardized form in Appendix A/B, and key parameters need to be jointly signed and confirmed by the shipowner

Loading PDF document...
Error loading PDF. Please make sure the file is valid and try again.
We also recommend
-

GB/T 39230-2020 in English
Code of practice for installation and commissioning of heavy duty submarine cable recovery and releasing device
2020-11-19 -

GB/T 39206-2020 in English
Code of practice for installation and commissioning of fixed azimuth thruster
2020-10-11 -

GB/T 39207-2020 in English
Code of practice for installation and commissioning of anchor handling system
2020-10-11