GB/T 33632-2017 in English
SUPERSEDEDGeneral installation requirements for aero-derivative gas turbine assembly
- Issued on:2017-05-12
- Implemented on:2017-12-01
- File Format:PDF
- Delivery:Via email within 1~3 business days
$175.00
《GB/T 33632-2017航空派生型燃气轮机成套设备安装通用技术要求》由TC259(全国燃气轮机标准化技术委员会)归口,主管部门为中国机械工业联合会。
Introduction
Interpretation of the National Standard of the People's Republic of China GB/T 33632—2017 General Technical Requirements for the Installation of Aviation-derived Gas Turbine Complete Equipment
Background and Significance of the Standard Formulation
The installation of aviation-derived gas turbine complete equipment is a complex and technically demanding project. The formulation of GB/T 33632—2017 aims to unify and standardize the installation process and technical requirements of such equipment to ensure that the installation quality reaches the highest level in the industry. The standard was proposed by the China Machinery Industry Federation and is managed by the National Technical Committee for Gas Turbine Standardization.
With the development of aviation technology, gas turbines are increasingly used in the field of power generation, and their installation technology is also evolving. The introduction of this standard provides a scientific and technical basis for related projects, and also lays the foundation for subsequent technology upgrades and equipment optimization.
Technical Specifications for Installation Preparation
Before installation begins, sufficient preparations must be completed, including verification of technical data, inspection of site conditions, and handover and storage of equipment. According to standard requirements:
- The layout of the construction site should comply with the construction organization design;
- The temperature of the construction site must meet the construction requirements;
- Transportation roads, water sources, power supplies and other facilities must be complete;
- The strength of the foundation concrete should not be less than 80% of the design strength.
| Inspection items | Allowable deviation range |
|---|---|
| Foundation coordinate position (vertical and horizontal axis) | ±20mm |
| Elevation of different planes of foundation | 0,-20 |
| Allowable deviation of equipment foundation size | ±20 -20 |
Key points for equipment placement and leveling
Before the equipment is placed, the foundation size needs to be checked and reviewed. According to the standard requirements, the measurement position for equipment alignment and leveling should select the main working surface of the equipment or the surface with higher processing accuracy. Special attention should be paid to the following:
- When installing the anchor bolt, any part should be more than 15mm away from the hole wall;
- The contact between the nut and the washer should be tight, and the feeler gauge cannot be inserted;
- Retest before secondary grouting, and ensure that the foundation surface is clean and moist.
Technical details of anchor bolts, washers and secondary grouting
During the installation process, the installation accuracy of the anchor bolt directly affects the stability of the equipment. According to Table 2, anchor bolts of different specifications have different torque and axial tension requirements.
| Bolt thread diameter (mm) | Torque (N·m) | Axial tension (kN) |
|---|---|---|
| 12 | 25~30 | 9 |
| 16 | 60~70 | 15 |
Suggestions for installation and commissioning of auxiliary equipment
During the installation of auxiliary equipment, special attention should be paid to the connection and sealing of the piping system. According to the standard requirements:
- All pipelines should be degreased and internally treated with anti-corrosion treatment before installation;
- Hose should be twisted when installed;
- The valve installation direction must be consistent with the medium flow direction.
Implementation suggestions and precautions
In order to ensure the installation quality of aviation-derived gas turbine complete sets, it is recommended to take the following measures:
- Construction organization design should be strictly carried out in accordance with standard requirements;
- Strengthen the record and acceptance of hidden projects;
- Pay attention to maintenance work after secondary grouting;
- Provide professional training for special operators.

Loading PDF document...
Error loading PDF. Please make sure the file is valid and try again.
We also recommend
-

GB/T 28686-2012 in English
Gas turbines thermodynamic performance tests
2012-09-03 -

GB/T 32821-2025 in English
Gas turbine applications—Safety
2025-08-01 -

GB/T 33631-2017 in English
General requirements for inlet and exhaust system of aero-derivative gas turbine assembly
2017-05-12 -

GB/T 42591-2023 in English
Gas turbine—Quality control specification
2023-05-23